An abnormally low tender is a bid whose price appears too low to deliver the requirement reliably, lawfully and to the stated standard.
Detailed explanation
A low price is not automatically unacceptable. Public buyers expect competition and may receive efficient offers from suppliers with better systems, lower overheads or a genuine commercial advantage. The concern begins when the price cannot readily be reconciled with the specification, programme, labour requirement, statutory obligations or normal market conditions.
For an SME, the risk is often accidental rather than deliberate. A pricing workbook may omit preliminaries, access equipment, supervision, disposal, inflation, travel, call-out cover or a subcontract package. An unrealistically low total can therefore signal that the bidder has misunderstood the scope, even where the quality submission is strong.
Where a buyer investigates, the supplier should be ready to explain its assumptions, build-up, productivity, supply-chain quotations and risk allowances. The explanation must be supported by evidence. A statement that the business is “keen to win the work” does not demonstrate that the price is sustainable.
Why it matters
Buyers may investigate whether the price is sustainable and whether the supplier has understood the scope.
How buyers use it
The buyer may compare the price against other tenders, its cost estimate, historic contracts and the stated delivery model. It may seek an explanation before deciding whether the tender is credible. The exact process depends on the procurement documents and applicable rules.
What suppliers should do
- Reconcile every pricing line with the specification and quality response.
- Record assumptions and exclusions before submission.
- Obtain written subcontractor and supplier quotations for material packages.
- Check labour hours, supervision, travel, access, waste, inflation and mobilisation.
- Prepare a clear price narrative where the tender permits one.
Where it fits in the process
- 1Tender submitted
- 2Buyer identifies unusual price
- 3Supplier explanation requested
- 4Evidence and assumptions reviewed
- 5Tender accepted or rejected
Frequently asked questions
Does the cheapest tender automatically win?
No. The buyer applies the published evaluation method. Price may carry significant weight, but mandatory requirements, quality scores and credibility still matter.
Can a buyer reject a low price without asking questions?
The applicable process depends on the procurement documents and legal regime. Suppliers should review the tender conditions and any formal request carefully.
What evidence supports a low price?
A transparent cost build-up, supplier quotations, productivity evidence, resource assumptions, delivery efficiencies and a clear explanation of how all contractual obligations remain funded.
Should we deliberately price below cost to enter a market?
That is a high-risk strategy. Consider cash flow, contract duration, inflation, performance exposure and whether the price remains sustainable throughout the contract.
What is the best prevention?
Use an independent commercial review and reconcile the pricing schedule against the specification, programme, method statements and risk register before submission.